Congratulations to the team at EFG Engineers (Pty) Ltd for the rapid progress on the road upgrade of MR168 between Lynedoch (km 5.88) and MR177 (km 10.62). According to Brian Domingo, Managing Director at EFG Engineers:

– The subbase layer is completed.
– Base layer construction is currently in progress.
– Asphalt activities are scheduled to begin in February.
– Trimming and placement of topsoil are underway on the completed carriageway.
– Paving of sidewalks is progressing well, enhancing accessibility and pedestrian safety.

Domingo explains: “We’re excited to see this project taking shape and look forward to the next phase of improvements! Stay tuned for more updates as we continue to enhance this critical route. The project came with challenges. We have appreciated Civil Designer’s intuitive and time-saving roadway rehabilitation features during the design process.”